17 December 2024

First 20 Vestas turbines installed at 220MW North Kyle

Brockwell Energy's flagship wind farm taking shape at former coal mining site

North Kyle 2min to read

Article originally published at Renews.biz, reproduced with permission.

Scottish developer Brockwell Energy has reached a key milestone at its flagship 220MW North Kyle wind farm in East Ayrshire, with the installation of the first 20 Vestas turbines.

The 49-turbine project is being built on the site of one of Scotland’s largest former coal mining sites.

The development began construction in 2023.

“This groundbreaking project has been delivered to a tight programme through challenging circumstances, whilst maintaining an excellent health and safety record,” said Richard Buckland, senior project manager at Brockwell Energy.

The wind farm will provide at least £65m in community benefits over its 40-year lifespan.
Mr Buckland said restoration benefits from construction alone are estimated to be worth at least £2.6m, with substantial additional investments including a further £2.6m in funding to East Ayrshire Council and £600,000 for broadleaf tree planting.

The company’s proactive approach has already delivered results, with wildlife returning to the site and extensive restoration work being carried out.

“There is good reason to be optimistic about the site’s future ecological improvements, and the regeneration of areas scarred by mining will leave a genuine legacy for the area,” Buckland added.
Elaine Stewart, MP for Ayr, Carrick, and Cumnock, said: “This project underscores the importance of placing local communities at the heart of renewable energy development.

“It is critical that the clean energy transition is fair, supportive, and deeply rooted in the needs of those it impacts.”

Mr Buckland said: “Looking ahead to 2025, and against the backdrop of the UK government aiming to double generating capacity by 2060 and expand onshore wind capacity substantially by 2030, Brockwell Energy’s achievements in East Ayrshire highlight real achievements in the renewable energy landscape.”

He added, however, that weather risk and key contractor programme delivery timescales remain key challenges to keeping the project on track for completion next year.
Common to the renewable energy sector, particularly, are potential delays in grid connections, with grid operator SP Energy Networks (SPEN) scaling up efforts to modernise the UK grid, he said.

“While we are encouraged by SPEN’s progress, grid connection delays represent a significant barrier to deploying renewable energy at scale,” Buckland noted.

“Specifically for North Kyle, it is of vital importance that SPEN delivers its programme to ensure the local and national benefits of North Kyle are realised on time.”